How to Load a Verge Ag Guidance export in a Trimble GFX/TMX monitor through Precision IQ
How to Load a Verge Ag Guidance export in a Trimble GFX/TMX monitor through Precision IQ
How to load the Setup file to the monitor through the Precision IQ app:
Create an export the Path Plan from Launch Pad
Copy the extracted folder (un-ziped) (AgGPS or AgData) to the root directory of the USB to transfer to the monitor
With the system powered up insert the USB
Click on the Precisoin IQ app
Click on "Data Transfer"
Select the data to be copied in the right column
Click Copy to copy the data from the USB to the internal storage on the monitor
How to Select a Field in the monitor that was loaded
From the main Precision IQ screen select the Field tile
Select the Filter Icon if you are not seeing the Fields that were loaded, they may be under a different Grower, Farm or Field that the list is currently filtered to
Select the Field you would like to use
To verify the lines are available click on the Field Settings Button
Click on the Guidance Patterns Tab
Select the Guidance you would like to use and activate.
Examples of Guidance Export options
Export AB Guidance
Export AB Guidance and Headlands
Export Inner Tracks and Headlands
Note: Trimble 750 and 2050 both run the Precision IQ app. The 2050 also allows the user to use the FMX Plus App to run guidance
Exporting Guidance Path Plans After a user has created their Path Plan(s), the next step is to export the plan. This article will walk you through the process and explain some of the options for Export. Users can export Plans while generating single ...
The procedure below shows how to load a setup file directly into a Deere Gen 4 monitor from the JDFile export in Launch Pad. How to load the Setup file to the monitor directly: Create and export the Path Plans from Launch Pad Copy the extracted ...
How to load the Setup file to the monitor directly: Ensure the monitor is powered down Remove the USB Copy the CN1 file that is on the USB to your computer as a backup of the data. This is highly recommended note: The monitor can not have more than ...
How to load the Setup file to the monitor Importing the ISO XML Taskdata folder After exporting the ISO XML TaskData from Launch Pad Extract the Taskdata folder and copy to the Root directory of a USB drive On the Monitor, with the System turned on ...
How to Sync/Update boundaries from Trimble Ag Online 1. While logged in, the user can manually request to update any modified Grower, Farm, Field and Boundary information from Trimble Ag Online. Click Menu and go to Land 2. Click the “Sync” button in ...